Pid Image
Project Director's Message
S.N. Name of Packages Total Quantity of work (KM) Grand Total Progress(Km%) Download
1 Bulk Distribution System 0 (Loan No -1820) 9.45 KM 9.45 Km 97.40 % -
2 Bulk Distribution System 1 (Loan No -2776) 10.96 Km 10.229 Km 92.70 % -
3 Bulk Distribution System 2 (Loan No -2776) 27.34Km 26.892 Km 97.88 % -
4 Bulk Distribution System - 3 (Loan No -2776) 14.85 Km 14.855 Km 100 % -
5 Bulk Distribution System - 4 (Loan No -3225) 14.39 Km 14.219 Km 94.98 % -
Total of 1, 2, 3, 4 & 5 76.99 Km 75.645 Km 98.25% -
SN Name of Packages Total Quantity of work (KM) Grand Total Progress(Km%) Download
1 Distribution Network Improvement Package -1 Pipe Laying : 302.00 KM H.H.C. : 26,889 Pipe Laying 301.382 Km H.H.C -23,705 -
2 Distribution Network Improvement I Package -2 Pipe Laying : 307.66 Km H.H.C : 30,684 Pipe Laying 301.327 Km H.H.C : 25,035 -
3 Distribution Network Improvement Package -3 Pipe Laying : 169.93Km H.H.C : 13,362 Pipe Laying 168.563 Km H.H.C. :12,408 -
4 Distribution Network Improvement Package -7A Pipe Laying : 227.29 Km H.H.C : 32,637 Pipe Laying 149.234 Km H.H.C : 9,512 -
Total of 1, 2, 3, & 4 Pipe Laying : 1006.88Km H.H.C : 1,03,572 Pipe Laying 920.506 Km H.H.C : 70,660 -
S.N. Title Download
1 पानी पोखरीको २०७६ जेष्ठ (जुन १५, २०१९) सम्मको प्रगति विवरण
2 Kathmandu Valley Water Supply Improvement Project, ADB Loan No. 3255 Quarterly Progress Report (October-December, 2018).docx
3 Bi-Annual Environmental Compliance & Monitoring Report --
4 Bi-annual Progress Report of Community Awareness and Participation Consultant (CAPC)
5 MPR_Oct --
S.N. Title Download
1 पानी पोखरीको २०७६ पाैष २९ (१४ जनवरी, २०२०) सम्मको प्रगति विवरण
2 पानी पोखरीको २०७६ म‌ंसिर ३० (डिसेम्वर १६, २०१९) सम्मको प्रगति विवरण
3 पानी पोखरीको २०७६ जेष्ठ (जुन १५, २०१९) सम्मको प्रगति विवरण
4 पानी पोखरीको २०७५ फागुन ३० (मार्च १४, २०१९) सम्मको प्रगति विवरण
5 पानी पोखरीको २०७५ माघ २९ ( फेब्रुअरी १२, २०१९ सम्मको प्रगति विवरण
Safeguard
  • Kathmandu Valley Water Supply Improvement Project, ADB Loan No. 2776 Quarterly Progress Report (October-December, 2018)
  • Kathmandu Valley Water Supply Improvement Project, ADB Loan No. 3255 Quarterly Progress Report (October-December, 2018)
  • Kathmandu Valley Water Supply Improvement Project – Additional Financing Environmental Monitoring Report (January-June 2018)
  • Kathmandu Valley Water Supply Improvement Project Social Monitoring Report (July-December 2017)
  • Kathmandu Valley Water Supply Improvement Project - Additional Financing Social Monitoring Report (July-December 2017)

Navigation

Social Media