Pid Image
Project Director's Message
S.N. Name of Packages Total Quantity of work (KM) Grand Total Progress(Km%) Download
1 Bulk Distribution System 0 (Loan No -1820) 9.45 KM 9.45 Km 97.40 % -
2 Bulk Distribution System 1 (Loan No -2776) 11.60Km 10.299 Km 89.18 % -
3 Bulk Distribution System 2 (Loan No -2776) 26.241 Km 26.380 Km 100 % -
4 Bulk Distribution System - 3 (Loan No -2776) 15.60 Km 14.855 Km 99.69 % -
5 Bulk Distribution System - 4 (Loan No -3225) 16.29 Km 13.652 Km 83.80 % -
Total of 1, 2, 3, 4 & 5 78.481 Km 74.566 Km 95.01% -
SN Name of Packages Total Quantity of work (KM) Grand Total Progress(Km%) Download
1 Distribution Network Improvement Package -1 Pipe Laying : 310.00 KM H.H.C. : 28,600 Pipe Laying 299.162 Km H.H.C -23,557 -
2 Distribution Network Improvement I Package -2 Pipe Laying : 303.8 Km H.H.C : 35,718 Pipe Laying 306.579 Km H.H.C : 25,018 -
3 Distribution Network Improvement Package -3 Pipe Laying : 169.00 Km H.H.C : 13,362 Pipe Laying 168.902 Km H.H.C. :12,408 -
4 Distribution Network Improvement Package -7A Pipe Laying : 226.26 Km H.H.C : 32,637 Pipe Laying 102.206 Km H.H.C : 6,509 -
Total of 1, 2, 3, & 4 Pipe Laying : 1009.06 Km H.H.C : 78,042 Pipe Laying 876.845 Km H.H.C : 67,492 -
S.N. Title Download
1 पानी पोखरीको २०७६ जेष्ठ (जुन १५, २०१९) सम्मको प्रगति विवरण
2 Kathmandu Valley Water Supply Improvement Project, ADB Loan No. 3255 Quarterly Progress Report (October-December, 2018).docx
3 Bi-Annual Environmental Compliance & Monitoring Report --
4 Bi-annual Progress Report of Community Awareness and Participation Consultant (CAPC)
5 MPR_Oct --
S.N. Title Download
1 पानी पोखरीको २०७६ जेष्ठ (जुन १५, २०१९) सम्मको प्रगति विवरण
2 पानी पोखरीको २०७५ फागुन ३० (मार्च १४, २०१९) सम्मको प्रगति विवरण
3 पानी पोखरीको २०७५ माघ २९ ( फेब्रुअरी १२, २०१९ सम्मको प्रगति विवरण
4 पानी पोखरीको २०७५ पौष ३० (जनवरी १४, २०१९ सम्मको प्रगति विवरण
5 पानी पोखरीको २०७५ मंसिर २९ ( डिसेम्वर १५, २०१८ सम्मको प्रगति विवरण
Safeguard
  • Kathmandu Valley Water Supply Improvement Project, ADB Loan No. 2776 Quarterly Progress Report (October-December, 2018)
  • Kathmandu Valley Water Supply Improvement Project, ADB Loan No. 3255 Quarterly Progress Report (October-December, 2018)
  • Kathmandu Valley Water Supply Improvement Project – Additional Financing Environmental Monitoring Report (January-June 2018)
  • Kathmandu Valley Water Supply Improvement Project Social Monitoring Report (July-December 2017)
  • Kathmandu Valley Water Supply Improvement Project - Additional Financing Social Monitoring Report (July-December 2017)

Navigation

Social Media