 TankaPrasad Ghumti Sadak

Government of Nepal
Melamchi Sub-Project 2

Kathmandu Upatyaka Khanepani Limited
Project Implementation Directorate (PID)

Progress Report

S.No. Name of Packages Total Quantity of Work (km) Cummulative Progress Percentage (km%) Download
Km %
1 Bulk Distribution System 0 (Loan No -1820) 9.46 km 9.46 km 100% -
2 Bulk Distribution System 1 (Loan No -2776) 11.26 km 11.06 km 98.22% -
3 Bulk Distribution System 2 (Loan No -2776) 27.00 km 26.97 km 98.22% -
4 Bulk Distribution System - 3 (Loan No -2776) 15.97 km 15.08 km 96.85% -
5 Bulk Distribution System - 4 (Loan No -3225) 14.29 km 14.01 km 98.03% -
6 Laying of Transmission Main from Sundarijal to Chabahil Chowk, and Construction of Related Civil Structures (KUKL/BDS-05) 25.78 Km 0.45 km 1.74% -
Total of 1, 2, 3, 4, 5 & 6 103.76 Km 77.31 Km 74.50 %
S.No. Name of Packages Total Quantity of Work (km) Cummulative Progress Percentage (km%) Download
1 Distribution Network Improvement Works (Package -1) KUKL/DNI/01/04 Pipe Laying : 303.03 KM
HHC: 26,889
Pipe Laying 303.03 Km
HHC: 26,484
-
2 Distribution Network Improvement Works (Package -2) KUKL/DNI/01/05 Pipe Laying : 320.17 Km
HHC : 30,634
Pipe Laying 317.01 Km
H.H.C : 25,849
-
3 Distribution Network Improvement Works (Package -3) KUKL/DNI/01/06 Pipe Laying : 168.83 Km
HHC : 12,414
Pipe Laying 168.83 Km
H.H.C. :12,409
-
4 Distribution Network Improvement Works (Package -4) KUKL/DNI/01/07A Pipe Laying : 228.06 Km
HHC : 32,637
Pipe Laying 228.06 Km
HHC : 17,583
-
5 Distribution Network Improvement Works (Package -5) KUKL/DNI-9A-01 KAPAN (GoN) Pipe Laying : 160.00 Km
HHC : 8229
Pipe Laying 69.02 Km
HHC : 4036
-
6 Distribution Network Improvement Works (Package -6) KUKL/DNI/01/7B (GoN) Pipe Laying : 224.37 Km
HHC : 25,132
Pipe Laying 96.10 Km
HHC : 6721
-
7 Distribution Network Improvement Works (Package -7) KUKL/DNI/01/7C (GoN) Pipe Laying : 249.18 Km
HHC : 19,960
Pipe Laying 103.18 Km
HHC : 6865
-
8 Distribution Network Improvement Works (Package -8) KUKL/DNI/9A-Mandikhatar (GoN) Pipe Laying : 130.29 Km
HHC : 14198
Pipe Laying 35.97 Km
HHC : 400
-
Total of 1, 2, 3, 4, 5, 6, 7 & 8 Pipe Laying : 1783.93 Km
HHC : 170,093
Pipe Laying 1321.20 Km
HHC : 100,711
-
S.No. Name of Packages Capacity (MLD) / Total Quantity of work (Km) Cummulative Progress Percentage (%) Download
Wastewater Treatment Plants (WWTPs)
1 Rehabilitation and Expansion of WWTPs at Guheshwori (TP-01) 32.4 MLD 100 -
2 Construction of WWTPs at Sallaghari, Kodku and Dhobighat (TP-02) 68.7 MLD 26.81
3 Construction of WWTP at Dhobighat (TP-03) 37 MLD 71.5 -
4 Construction of DEWATS at Gokarna and Hanumanghat (DEWATS-01) 3.5 MLD 0.5 -
Interceptors/ Sewer Network Total Quantity Of Work(KM) Cummulative Progress (KM)
5 Construction of Intercepting Sewerage System along Hanumante River (IS-01) Pipe Laying : 25.33 Km 16.83 Km -
6 Extension and Construction of Intercepting Sewerage System along Manohara River (IS-02) 11.63 Km 5.82 Km
7 Construction of Sewer Collectors along Kashyang Khusung River (IS-03) 7.67 Km 7.1 Km
8 Sewer Rehabiliation in the Core City of Area of Lalitpur Municipality City (SN-03) 2.8 Km 1.14 Km
9 Baluwatar Storm water Management Works 1.23 Km 0.656 Km
S.N. Title Location Capacity Cummulative Progress Percentage (%) Download
S.N. Title Download
1 आयोजना कार्यन्वयन निर्देशनालयको आ. व. २०७६/०७७ को वार्षिक प्रगति विवरण
2 पानी पोखरीको २०७६ जेष्ठ (जुन १५, २०१९) सम्मको प्रगति विवरण
3 Kathmandu Valley Water Supply Improvement Project, ADB Loan No. 3255 Quarterly Progress Report (October-December, 2018).docx
4 Bi-Annual Environmental Compliance & Monitoring Report --
5 Bi-annual Progress Report of Community Awareness and Participation Consultant (CAPC)
S.N. Title Download

Progress Report

S.No. Name of Packages Total Quantity of Work (km) Grand total Progress (km%) Download
1 Bulk Distribution System 0 (Loan No -1820) 9.46 km 9.46 km (100%) -
2 Bulk Distribution System 1 (Loan No -2776) 11.26 km 11.06 km (98.22%) -
3 Bulk Distribution System 2 (Loan No -2776) 27.00 km 26.97 km (99.88%) -
4 Bulk Distribution System - 3 (Loan No -2776) 15.97 km 15.08 km (96.85%) -
5 Bulk Distribution System - 4 (Loan No -3225) 14.29 km 14.01 km (98.03%) -
Total of 1, 2, 3, 4 & 5 77.58 km 76.58 km (98.71%)
S.No. Name of Packages Total Quantity of Work (km) Grand total Progress (km%) Download
1 Distribution Network Improvement Package -1 Pipe Laying : 303.03 KM H.H.C. : 26,889 Pipe Laying 303.03 Km H.H.C.:26,484 -
2 Distribution Network Improvement Package -2 Pipe Laying : 320.17 Km H.H.C : 30,634 Pipe Laying 312.21 Km H.H.C : 25,562 -
3 Distribution Network Improvement Package -3 Pipe Laying : 168.43 Km H.H.C : 12,414 Pipe Laying 168.83 Km H.H.C. :12,409 -
4 Distribution Network Improvement Package -7A Pipe Laying : 227.29 Km H.H.C : 32,637 Pipe Laying 199.18 Km H.H.C : 11,285 -
Total of 1, 2, 3, & 4 Pipe Laying : 1019.42 Km H.H.C : 1,03,572 Pipe Laying 983.25 Km H.H.C : 75,740 -
S.No. Name of Packages Capacity (MLD) / Total Quantity of work (Km) Grand total Progress (%) Download
Wastewater Treatment Plants (WWTPs)
1 Rehabilitation and Expansion of WWTPs at Guheshwori (TP-01) 32.4 MLD 100 -
2 Construction of WWTPs at Sallaghari, Kodku and Dhobighat (TP-02) 68.7 MLD 26.81
3 Construction of WWTP at Dhobighat (TP-03) 37 MLD 71.5 -
4 Construction of DEWATS at Gokarna and Hanumanghat (DEWATS-01) 3.5 MLD 0.5 -
Interceptors/ Sewer Network
5 Construction of Intercepting Sewerage System along Hanumante River (IS-01) Pipe Laying : 25.33 Km 16.83 Km -
6 Extension and Construction of Intercepting Sewerage System along Manohara River (IS-02) 11.63 Km 5.82 Km
7 Construction of Sewer Collectors along Kashyang Khusung River (IS-03) 7.67 Km 7.1 Km
8 Sewer Rehabiliation in the Core City of Area of Lalitpur Municipality City (SN-03) 2.8 Km 1.14 Km
9 Baluwatar Storm water Management Works 1.23 Km 0.656 Km
S.N. Title Download
1 आयोजना कार्यन्वयन निर्देशनालयको आ. व. २०७६/०७७ को वार्षिक प्रगति विवरण
2 पानी पोखरीको २०७६ जेष्ठ (जुन १५, २०१९) सम्मको प्रगति विवरण
3 Kathmandu Valley Water Supply Improvement Project, ADB Loan No. 3255 Quarterly Progress Report (October-December, 2018).docx
4 Bi-Annual Environmental Compliance & Monitoring Report
5 Bi-annual Progress Report of Community Awareness and Participation Consultant (CAPC)
S.N. Title Download
1 पानी पोखरीको २०७७ माघ ३० (February, 15, 2021) सम्मको प्रगति विवरण
2 आयोजना कार्यान्वयन निर्देशनालयको चैत्र महिना सम्मको प्रगति विवरण
3 आयोजना कार्यन्वयन निर्देशनालयको माघ महिना सम्मको प्रगति विवरण
4 पानी पोखरीको २०७६ माघ २९ (१४ फेब्रुअरी १२ , २०२०) सम्मको प्रगति विवरण
5 आयोजना कार्यन्वयन निर्देशनालयकाे, पौष महिना सम्मको प्रगति विवरण